Can an allottee who did not urge earlier later on withdraw from the project?

In the course of implementation of RERA Act 2016, the Authorities face various unique challenges in deciding over the question of law or question of fact every day.

What to do if the RERA order is not being complied with

RERA Authority order is not being complied with by the party or if we are precise, the builder is not paying the amount ordered by authority.

Proceed to NCLT for recovery of dues under Insolvency & Bankruptcy Code

To initiate recovery procedure one can approach the National Company Law Tribunal which exercises the power to dispose cases under Insolvency Code.

Agreement to lease falls within the scope of RERA

  The Real Estate Industry in India has seen a drastic change after the Real Estate (Regulation and Development) Act, 2016 (RERA) coming into picture. Though the Act is applicable to all the states of the country but Maharashtra seems to be quickest amongst all. The Maharashtra Real Estate Regulatory Authority (MahaRERA) and the Adjudicating … Continue reading “Agreement to lease falls within the scope of RERA”

No possession date, no RERA relief, rules MahaRERA

MahaRERA has dismissed a complaint from a home buyer against India Bull Real Estate Ltd for delayed possession ruling that since no possession date was given by the developer, RERA provisions do not come into play to provide any relief.