NCDRC vs RERA vs IBC, Which Is the best mechanism for consumers to get timely relief

Supreme Court allowed several buyers to join their suit property in order to increase valuation of their dispute and approach the NCDRC however buyers still find it difficult to get timely relief from the NCDRC.

Bombay High Court: Deposit 50% of the refund amount to hear the case

The high court upheld the decision of the Appellate tribunal by directing the builder to deposit the 50% of the refund amount as ordered by the authority in order to hear the plea.

IBC- Greatest rescue for the homebuyers

If there is no assured return plan incorporated into the builder buyer agreement entered into between the homebuyer and builder then the homebuyer had to approach RERA to seek refund.

RERA: No advertisement of the project without RERA Registration

Issues arise that if the project is a new project then it is mandatory for the promoter to get it registered before marketing the same. But what if the project is an ongoing project?

Assured Returns: Not for Real Estate Projects

The Gurugram RERA known as H-RERA is about issue a notification for the builder who are trying attracts the home buyers by making an offer of ‘Assured Returns’.

An overview of RERA implementation in Gujarat

After the implementation of the RERA Act, the State of Gujarat has notified its final Gujarat RERA Rules, 2017 on 29.10.2016 which prescribes regulation, form and process.

Should Home Buyer under RERA be given preference under Insolvency And Bankruptcy Code, 2016

IBC and RERA Act, enacted in 2016, appear to be pitted against each other as far as protecting the interests of bankers and home buyers are concerned.

Filing of RERA complaint as an association

There has been huge confusion with respect to filing of complaint as association. An association of persons with respect to a particular project may file a case against the builder.

Newly Formulated Greater Noida Bench of RERA- The story so far

Western UP Bench of RERA- After looking at the bulk cases in the state a bench was made operational in the city of Noida on 4th September, 2018.

UP RERA orders Ansal API to resolve the issues within a week

In the cases against Ansal API Group one of the member Mr. Balwinder Singh has ordered Ansal Properties & Infrastructure Pvt. Ltd. to dispose off the grievances of the allottee within a week.

Supreme Court to the rescue of Amrapali and Unitech Homebuyers

An order passed by the supreme court in favour of the aggrieved home buyers who have been waiting to get justice against named builders of the country which is the AMRAPALI Group and UNITECH.

Homebuyers get a relief under the Insolvency and Bankruptcy Code, 2016

Homebuyer is a person who buys or expects to buy a house. And A promoter is an individual or organization that helps raise money for some type of investment activity.