Citation
2017/UP/Centrik/1/UPRERA
Party to the case
Alok Babbar Vs. M/s Supertech Ltd
Brief Facts
The complainant alleged the builder for delayed possession and filed the complaint on the basis that as per the builder buyer agreement, date of possession is 31/8/2017 but the respondent failed and delayed the possession as the work is not complete till date.
Held
The complaint was dismissed as both the parties were not present for the hearing
Authority
UP RERA
Month/Year
November 2017