Citation
2018/UP/Centrik/18/UPRERA

Party to the case
Mr. Pravin Kumar Gambhir Vs. M/s Greenbay Infrastructures Pvt. Ltd.

Brief Facts
The present complaint was filed by the complainant seeking the refund of the amount paid till date along with an interest of 24% due to delay in possession by the builder.

Held
The authority held that the complainant can get the possession of the property after paying the remaining amount to the respondent and directed the respondent to give possession of the property within a month. Also, if the complainant is unwilling to take possession of the property, he is entitled to refund of the amount paid by him without any interest within 45 days of receiving the order.

Authority
UP RERA

Month/Year
January 2018