The Real Estate (Regulatory and Development) Act, 2016 is the first regulations in Real Estate Sector to regularize. At one place, where the Act specifies the details rules and regulation for proper registration and transparency, the Act also prescribes penalty for different kind of offenses.
We are summarizing offence-wise penalties so that right compliance can be done at right time.
A. Offence-wise Penalties for Promotors
S. No | Offence | Penalty |
1. | Non-registration of a project | 10% of the estimated cost of real estate project |
2. | Not obeying orders or direction in connection with the above offence | Imprisonment upto 3 years with an or without fine being 10% of the estimated cost of real estate project |
3. | Providing false information etc. | 5% of the estimated cost of real estate project |
4. | Other contravention | 5% of the estimated cost of real estate project |
5. | Contravention of any order of the RERA | Penalty for every day of defaults which may cumulatively extend up to 5% of the estimated cost of real estate project |
6. | Contravention of the orders or direction of the appellate tribunal | Imprisonment upto 3 years with or without fine which may cumulatively up to 5% of estimated cost of real estate project. |
B. Offence-wise Penalties for Real Estate Agents
S.No | Offences | Penalties |
1. | Contravention of the applicable provisions of the Act | Rs. 10,000 per day of defaults which may extend up to 5% of the cost of the property whose sale or purchase was facilitated by him |
2. | Contravention of the orders or direction of the RERA | Penalty on a daily basis which may cumulatively extend up to 5% of the estimated cost of the property whose sale or purchase was facilitated by the agent |
3. | Contravention of the orders or direction of the appellate tribunal | Imprisonment upto 1 year with without fine which may extend up to 10% of estimated cost of project. |
C. Offence-wise Penalties for Allottees
S.No. | Offences | Penalties |
1. | Contravention of any order of the RERA | Penalty for the period during which defaults continues which may cumulatively extend up to 5% of the apartment or building cost |
2. | Contravention of the orders or direction of the appellate tribunal | Imprisonment upto 1 year with or without fine for every day during which such defaults continues, which may cumulatively extend up to 5% of the apartments or building cost. |
For more information and details, please write us at info@centrik.in
Dear Sir
case is going on District court, than, can we file complaint against builder in RERA.
Plot was purchased at asohna Road in march 2012, till may, 2017 builder received part completion certificate, will it come under RERA in Gurgaon. Completion certificate for phase 1 is taken in June, 2018. As per Bombay high court decision, will it come under ambit of RERA. PROJECT NAME : RAHEJA ARANYA CITY
It would depend on other facts as well. Please mail us at rera@centrik.in so that our expert can advise
Kindly advise on the above points
How a builder can put his signboard in front of our Society,wihout RERA’s registration ? Name of he Builder : SHYAMVIJAY INFRASTRUCTURE ,Satellite,Ahmedabad – 380015. Name of Society : ASHIRWAD APPTS,OPP ; DENA BANK,OPPOSITE : RAS MADHUR SWEET HOME,BHIMJIPURA, NAWA VADEJ, AHMEDABAD : 380013.A complaint against a builder M/s.SHYAMVIJAY INFRASTRUCTURE,Sattelltte, AHMEDABAD 380015.who has placed a sign board in front of ASHIRWAD APPARTMENTS, OPPOSITE: RAS MADHUR SWEET HOME BHIMJIPURA,NAWA VADEJ, AHMEDABAD-380013, for an advertisement dated :10/10/2018,without getting RERA’s Registration / Permission.
The advertisement before RERA registration may attract penalty as per RERA Act. Please file a complaint before the Gujarat RERA
Sir,I have made a Complaint in writing to RERA office,GUJARAT REAL ESTATE REGULATORY AUHORITY
Dr.Manjula.A.Subramanium.
( IAS Retired )CHAIRPERSON RERA,
Chief township Planning and Valuation Office.
opp : St.Xavier’s School,
Gandhinagar.
Gandhinagar dated 16/11/2018 and
one more on 30/11/2018 to GUJARAT REAL ESTATE REGULATORY AUHORITY,( APNA RERA)
RERA AUTHORITY / RERA ADJUDICATING OFFICER ,
( RERA COMPLAINT REDRESSAL ) 4 th floor,Sahyog Building,
GH-Road,Sector-11,
Near Pathik Ashram,
Gandhinagar : 382010. through registered A.D.
NO REPLY & NO ACTION TAKEN TILL DATE.
Can we filed a complaint against builder for poor quality construction. Because of heavy rainy days the flats from top floor of 11 store building and it’s leaking from dealings.
yes you can file for structural issues